A strip out and excavation to determine to cause of a leak within an indoor swimming pool.

After detection of a water leak under the cement screed of the swimming pool, Knoetze were asked to commence the strip out works just before christmas, 2019. Instructions were to thoroughly protect the site before removing a huge area of floor tiles, screed and insulation, as well as 1m of wall plaster to leave ready for reinstatement in the New Year. The whole pool house was excavated and removed from site within three days with a team of six. This was no small feat, as it was five full, six yard skips to remove from site with a 40 metre stroll between site and skip!
Away from home just before the festive period encouraged a christmas staff meal in a curry house in Newbury! What a night it was!